Outlines and timetables for the expansion and renovation of the Washington Irving School were presented at the final EPTA meeting held at John Paulding on May 30.
|
Rendering of Washington Irving School Facing West |
• July '06 - August '06: Temporary music rooms setup in the back of the auditorium on the first floor.
• October '06 - November '07: Construction and renovation of classrooms on the ground floor. Construction of music rooms and renovation of boys' bathroom and classrooms on the first floor. Renovate boys' bathroom and classrooms on the second floor.
• December '07 - January '08: Renovation of classrooms on the first floor and second.
• July '08 - August '08: Construction of temporary classrooms in the cafeteria on the ground floor.
• July '08 - December '08: Renovation of auditorium and administration on the first floor. Renovation of the upper auditorium and a full-size library on the second floor. Renovation of third floor.
• January '09 - June '09: Renovation of girls' bathroom and classrooms on the first floor and second floor.